40 GIgabit Ethernet Networks – Direct Uplink vs Fan-Out Uplink

fan-out cableFan-out cable is considered as one of the the latest enabling technologies to help increase port densities and lower costs. Taking one (large bandwidth) physical interface and breaking it out into several (smaller bandwidth) interfaces, it is now recommended to use for network migration. In this post, I will compare the 40G direct uplink and the fan-out 4x10G uplink configurations and their inherent difference in maximum server scalability.

For a leaf/spine network architecture, the number of connections used for uplinks from each leaf switch determines the total number of spine switches in the design. Meanwhile, the number of ports on each spine switch determines the total number of leaf switches.

Now, image that we will build a network that supports 1200 10G servers in one fabric with 2.5:1 oversubscription. The network must seamlessly expand to over 5000 10G servers without increasing latency or oversubscription in the future. Next, I will compare two different approaches.

40G Leaf/Spine Fabric – With 40G QSFP Uplink

The following picture shows us a 40G fabric to us. Each of the spine switches has 32 ports of 40G. Each leaf ToR (Top of Rack) switch is connected to the spine with 4 ports of 40G using the leaf switches 40G QSFP uplink ports. There will be 40 servers per rack connected to each leaf switch. Namely, it allows a maximum is 1280 x 10G servers at 2.5:1 oversubscription. This meets the initial scale target of 1200 servers however, it cannot scale larger. Before the network can achieve the 5000 server design goal, the 40G design will have to be re-architected.

40G Fabric

10G Leaf/Spine Fabric

As mentioned above, a direct 40G uplink is not an ideal configuration for a cost-effective server scalability. So, what level of server scalability can be achieved when using fan-out the leaf switch uplink ports with 4 x 10 G each?

The picture below shows a 10G leaf/spine fabric to us. With a QSFP+ to SFP+ optical fan-out cable, each QSFP leaf port is now fanned out to 4 x 10G interfaces each, for a total of 16 x 10G uplinks. Each of the spine switches now has 128 ports of 10G. Each leaf switch is connected to the spine with 16 ports of 10G. In this case, the maximum scale is 5120 x 10G servers at 2.5:1 oversubscription. Obviously, with the same bandwidth, latency and oversubscription, this fabric is better. It can not only be built to 1200 servers for present demand but also can seamlessly scale to over 5000 servers in the future.

10G Fabric

In a word, the 10G leaf/spine fabric design offers 4X greater scalability compared to the 40G fabric design with same hardware, bandwidth, latency and oversubscription. These two configuration scenarios show us how fan-out technology may be used to scale up a data center fabric. As the 10G network is widely deployed in today’s data center, but high speed demand such 40/100G is needed. The fan-out technology not only helps to enables new levels of server scalability, but also helps save time and cost for network migration.